Construction related traffic impacts are subject to change and dependent on favorable weather patterns. Ashland County Highway: US 2 Location: Ashland, Lake Shore Drive, Beaser Avenue Schedule: April 2009-June 2009 Cost: $12 million Description: ...

Construction related traffic impacts are subject to change and dependent on favorable weather patterns.

Ashland County

Highway: US 2

Location: Ashland, Lake Shore Drive, Beaser Avenue

Schedule: April 2009-June 2009

ADVERTISEMENT

Cost: $12 million

Description: Contractors are putting the final touches on the urban reconstruction project that took place in 2008, including completing work on the parapet and railing on the large retaining wall on the north side of the road overlooking the hot pond.

Traffic Impact: Intermittent lane closures

Barron County

Highway: US 53

Location: Southbound bridge over County SS

Schedule: June 3-August 10, 2009

Cost:

ADVERTISEMENT

Description: Resurface bridge deck

Traffic impact: The project will be done half at a time. Traffic is one lane on southbound US 53 with a 14 foot lane width restriction.

Bayfield County

Highway: WIS 27

Location: South County Line-West County Line

Schedule: May 27-June 25, 2009

Cost: $231,992

Description: Culvert replacement project

ADVERTISEMENT

Traffic Impact: WIS 27 is closed to thru traffic from County N to the Sawyer/Bayfield county line. The detour uses Bayfield County N to US 63 south to Hayward. Residents and emergency vehicles will be allowed access.

Highway: WIS 13

Location: City of Washburn

Schedule: June 8-18, 2009

Cost: $259,000

Description: Resurface project

Traffic Impact: Single lane restrictions with flagging crews during daytime hours only

Buffalo County

ADVERTISEMENT

Highway: WIS 35

Location: Between Alma and WIS 37

Schedule: May 13-July 31, 2009

Cost: $291,000

Description: Bridge reconstruction project

Traffic Impact: One lane road with temporary signals

Burnett County

No state construction projects currently in progress

ADVERTISEMENT

Chippewa County

Highway: WIS 27

Location: Lake Holcombe

Schedule: March 27-October 16, 2009

Cost: $3.7 million

Description: Bridge replacement project over the Holcombe Flowage

Traffic Impact: Single lane closures with the use of flagging crews

Highway: WIS 124

ADVERTISEMENT

Location: Chippewa Falls, Bridge Street (BUS 29 over WIS 124) and Eau Claire-Chippewa Falls Road (US 53 to BUS 29).

Schedule: April 13-October 16, 2009

Cost: $6.9 million

Description: Removing interchange and replacing it with a roundabout at the same location

Traffic Impact: WIS 124 north and southbound traffic is operating on the existing WIS 124 southbound lanes. Business 29 east and westbound traffic is operating on the existing Business 29 westbound lanes. In conjunction with this project, WIS 124 is being resurfaced. The outside driving lanes of WIS 124 northbound and southbound are closed from County OO to Woodward Avenue until August 13.

Highway: US 53

Location: Chippewa River Bridges near Business 29 exit

Schedule: April 20-August 28, 2009

Cost: $687,737

Description: Bridge painting

Traffic Impact: Left lane closed in both the north and southbound lanes of US 53

Highway: WIS 64

Location: McCann Creek Bridge between Bloomer and Cornell Road

Schedule: May 11-July 9, 2009

Cost: $496,440

Description: Removal and replacement of the bridge

Traffic Impact: WIS 64 is closed with local traffic access from the east and west. A detour route is marked as follows: Eastbound WIS 64 to County GG southbound to County SS eastbound to WIS 124 northbound to WIS 64 eastbound. Reverse for the westbound traffic.

Clark County

No state construction projects currently in progress

Douglas County Project is complete

Dunn County

No state construction projects currently in progress

Eau Claire County

Highway: US 53

Location: Hastings Way/Birch Street in the city of Eau Claire

Schedule: March 24-November 6, 2009

Cost: $8.7 million

Description: Removing the Birch Street Bridge and constructing an at-grade intersection with stop lights.

Traffic Impact: Birch Street Bridge over Hastings Way is closed. Traffic will no longer be able to go east on Birch Street from the west ramps (Hastings Way). New detour routes are signed for Birch Street east using Seymour Road.

Highway: I-94

Location: Between WIS 312 and WIS 29 (On the Eau Claire County/Dunn County line)

Schedule: April 2-June 30, 2009

Cost: $4 million

Description: Bridge replacement project

Traffic Impact: Four lanes of traffic (two eastbound and two westbound) are using the westbound roadway (section of the bridge that was replaced last summer). Evergreen Road under I-94 will be closed until June 30. It is anticipated traffic will be back on their respective roadways the week of June 15.

Jackson County

Highway: I-94

Location: Black River Falls to Tomah Road (County O to County EW)

Schedule: April 9 - September 16, 2009

Cost: $9.7 million

Description: Concrete pavement repair, new guardrails, and widening and redecking four bridges.

Traffic Impact: County O, Aspen Avenue and County EW under I-94 have intermittent flagging operations. Westbound I-94 has two 11 foot lanes around each of the four structures on the project. This will be a continuous lane restriction from approximately 1.5 miles east of County EW to approximately one-half mile west of County O.

Highway: WIS 54

Location: Galesville-Melrose Road (Back Street-Salvage Road)

Schedule: May 11-June 5, 2009

Cost: $193,000

Description: Storm sewer reconstruction, new asphalt and curb and gutter

Traffic Impact: Single lane with the use of flagging crews (Project is expected to be completed on Friday, June 5)

Jackson and Trempealeau Counties

Highway: I-94

Location: Osseo-Black River Falls Road (West county line-WIS 95)

Schedule: April 15-July 31, 2009

Cost: $7.1 million

Description: Pavement resurface project

Traffic Impact: Single lane closures on eastbound I-94 from Northfield to Hixton with reduced speed to 55 mph from Monday-Friday.

Pepin County

No state construction projects currently in progress

Pierce County and St. Croix Counties

Highway: US 63

Location: WIS 29 to I-94 (Ellsworth -Baldwin)

Schedule: March 20-August 4, 2009

Cost: $3.3 million

Description: Bridge replacement and paving with miscellaneous construction

Traffic Impact: Traffic is reduced to one lane and controlled with traffic signals at the location of the bridge replacement. Single lane closures may occur throughout the project with flagging operations.

Pierce County

Highway: WIS 65

Location: Ellsworth-River Falls Road

Schedule: May 12-July 31, 2009

Cost: $4.2 million

Description: Resurface project

Traffic Impact: Multiple single lane closures will be present throughout the 10 mile project area. Flagging personnel will be directing traffic through lane closures, primarily between 6 a.m.-8 p.m. Monday through Saturday.

Polk County

No state construction projects currently in progress

Rusk County

No state construction projects currently in progress

St. Croix County

Highway: WIS 64

Location: New Richmond-Connorsville Road/WIS 65-US 63

Schedule: May 28-October, 9 2009

Cost: $4.1 million (American Recovery and Reinvestment Act project)

Description: Resurface roadway and make safety improvements to the WIS 64/ County T intersection.

Traffic Impact: Periodic lane closures with flaggers directing traffic

Sawyer County

No state construction projects currently in progress

Taylor County

No state construction projects currently in progress

Washburn County

No state construction projects currently in progress

What To Read Next
Get Local

ADVERTISEMENT